Mumbai: Adani Green Energy’s proposed 1,500-megawatt Tarali Pumped Storage Project in Maharashtra’s Satara district has suffered a setback after the state Forest Department ordered an immediate halt to construction activities. The department cited the absence of mandatory prior approval from the National Board for Wildlife (NBWL).
The stop-work order was issued on November 13 for the project located in Patan taluka. The department has also issued a notice asking the company to explain within three days the basis on which construction began without the required wildlife clearance. It has sought documents relating to statutory approvals, project maps and permissions for tree felling. Further legal action has been warned if the company fails to provide a satisfactory response.
The project is proposed across 150.74 hectares of non-forest land in Nivade, Tondoshi, Kalambe and Jalu villages. It envisages using the existing Tarali reservoir as the lower reservoir and developing a new upper reservoir to generate electricity through pumped storage technology.
The project has also come under scrutiny over a major revision in its declared cost. While environmental clearance documents listed the estimated cost at ₹5,675 crore, a company affidavit cited ₹56.75 crore. This has raised questions over the proposed contribution to the Sahyadri Tiger Reserve’s conservation fund.
Adani Green Energy has denied allegations of regulatory violations. The company maintains that ₹56.75 crore relates only to preliminary survey and investigation work, not the total project cost. It has stated that construction began after obtaining the requisite approvals and that its wildlife clearance proposal is under consideration.
The Forest Department’s order is an interim measure and does not amount to cancellation of the project.