Delhi’s first double-decker flyover, being constructed between Yamuna Vihar and Bhajanpura in northeast Delhi, has suffered another setback. The ₹291.10-crore project, earlier scheduled for completion by December 2026, has now been postponed until March 2027 due to construction restrictions imposed under the Graded Response Action Plan (GRAP) to control air pollution.
The delay means commuters in northeast Delhi will have to wait another three months for relief from traffic congestion along one of the region’s busiest routes.
Metro Operational, Road Section Incomplete The 1.40-kilometre-long structure is designed with a Metro corridor on the upper deck and a four-lane road flyover beneath it. Metro services on the upper section began on March 8, 2026, but motorists are still unable to use the lower section because road surfacing and approach ramps on both sides remain unfinished.
Once operational, the flyover is expected to improve traffic movement between Yamuna Vihar, Bhajanpura, Ghonda, Karawal Nagar and Brijpuri.
Project Faces Repeated Deadline Extensions Announced in 2019 with an initial estimated cost of ₹220.10 crore, the project later received a revised cost approval of ₹291.10 crore. Its original completion deadline was December 2024, but the timeline was extended several times.
Earlier, delays in obtaining permission for tree felling and transplantation affected construction for nearly two years. After receiving the necessary clearances, the Delhi Metro Rail Corporation initiated fresh tendering for the remaining work, including the approach ramps.
March 2027 Is the New Target
The latest GRAP restrictions have further slowed construction, with dust-generating external work temporarily halted under pollution-control measures. Ghonda MLA Ajay Mahawar said he was coordinating with the concerned agencies to accelerate the remaining work once restrictions are lifted.
The project is expected to provide significant relief to commuters in northeast Delhi, but residents will now have to wait until March 2027 for the road section to become operational.